February 2024 Community Updates
Posted By mplascencia on February 26, 2024
Dear Residents,
the schedule has changed as they are anticipating 2 days for each floor in Building 2 and 3-4 days for each floor in Building 1. If some floors are easier than others, the schedule will be updated at that time.
Below is an updated schedule by floor. The dates may be subject to change:
• Mon, Feb 19th & Tue, Feb 20th: Building 2 – Sixth Floor
• Wed, Feb 21st & Fri, Feb 23rd: Building 1 – Fifth Floor
• Mon, Feb 26th & Thu, Feb 29th: Building 1 – Fourth Floor
• Mon, Mar 4th & Thu Mar 7th: Building 1 – Third Floor
• Mon, Mar 11th & Thu, Mar 14th: Building 1 – Second Floor
• Mon, Mar 18th & Thu, Mar 21st: Building 1 – First Floor
Please note the following ahead of the carpet installation:
• During the hours of work, if access is needed in or out of the area being worked, please call out for an installer to assist. (especially if there is caution tape on your door). This includes the elevator access point on the floor being worked.
• The area needs to be undisturbed during the installation process.
• No moves/deliveries can take place on your floor during the carpet installation process. If you are expecting a package, please check the mailbox area as delivery carriers may not be able to bring packages to your floor.
• Loud construction noise is expected to occur. Please plan accordingly.
Should there be any changes to the carpet installation schedule, Management will provide an update. If you have any questions, please contact Management at pbwgm@actionlife.com.